The final circuits completed the Trial Run Test at the end of February. At the same time, work was underway at the farm on the demolition of the temporary elements of the road system (which will be redundant during the operational period), the implementation of the permanent exits to the county roads and the national road, and the clean-up work to obtain the TOC, or Certificate of Completion. The application process for an Occupancy Permit was also underway. On 18 February, BBFW obtained the Permit to Use for Phase I of the project consisting of the 110kV cable line connecting the BBFW 30/100kV GPO (Main Receiving Point of the farm to the NPS), the GPO, the T26 turbine and the infrastructure. Production in February reached an above-average result of 47 GWH