Temporary pavements 70% complete. Fiber optics for MV lines blown into pipelines. 110kV cable along with fiber optic line ready. MV and control cables are being laid at the GPO grass, control cabinets and MV switchgear are being installed. The first 85MVA power transformer is arriving at the construction site. As part of the agreement on the implementation of compensation investments in the municipality of Biały Bór, the company purchased a fire truck for the Drzonowo TSO.