BB Farma Wiatrowa Sp. z o.o. Biała 60 78-425 Biały Bór NIP: 583 297 86 70 KRS: 0000274599
BB Farma Wiatrowa Sp. z o.o.
Biała 60
78-425 Biały Bór
NIP: 583 297 86 70
KRS: 0000274599
Mechanical assembly of all 42 turbines has been completed. Internal inspections of the so-called walkdowns by turbine supplier Vestas are …
Continue reading “2021 November”
On October 27, PSE issued a permit for wind turbines to begin generating power to the grid.WF Biały Bór received …
Continue reading “2021 October”
On September 1, PSE energized the high-voltage cable line connecting the 400/220/110kV Żydowo-Kierzkowo SE ZDK substation with the Bialy Bor …
Continue reading “2021 September”
Pre-installation, i.e. the installation of the first two tower segments on all sites, has been completed. Preinstallation was carried out …
Continue reading “2021 August”
Delivery and installation of V126 turbines with a capacity of 3.45MW and a height of HH117m has begun. Each turbine …
Continue reading “2021 July”
Zakończono realizacje fundamentów jest gotowość do przekazania ich do montażu turbin. Na GPO trwają prace rozruchowe dostarczono dławik WN. Dostawca …
Continue reading “2021 June”
Temporary pavements 70% complete. Fiber optics for MV lines blown into pipelines. 110kV cable along with fiber optic line ready. …
Continue reading “2021 May”
Pile work has been completed, 41 foundations concreted. HV cable laid – the couplers have been made it remains to …
Continue reading “2021 April”
Winter has let up 38 foundations concreted. Installation of fiber optic lines tied to MV cable lines began. 110kV cable …
Continue reading “2021 March”
Still severe weather conditions but 20 foundations concreted, halfway point in a while. MV cable laying completed. 110kV cable 50% …
Continue reading “2021 Febuary”
You cannot copy content of this page