On September 1, PSE energized the high-voltage cable line connecting the 400/220/110kV Żydowo-Kierzkowo SE ZDK substation with the Bialy Bor …
Continue reading “2021 September”
Pre-installation, i.e. the installation of the first two tower segments on all sites, has been completed. Preinstallation was carried out …
Continue reading “2021 August”
Delivery and installation of V126 turbines with a capacity of 3.45MW and a height of HH117m has begun. Each turbine …
Continue reading “2021 July”
Zakończono realizacje fundamentów jest gotowość do przekazania ich do montażu turbin. Na GPO trwają prace rozruchowe dostarczono dławik WN. Dostawca …
Continue reading “2021 June”
Temporary pavements 70% complete. Fiber optics for MV lines blown into pipelines. 110kV cable along with fiber optic line ready. …
Continue reading “2021 May”
Pile work has been completed, 41 foundations concreted. HV cable laid – the couplers have been made it remains to …
Continue reading “2021 April”
Winter has let up 38 foundations concreted. Installation of fiber optic lines tied to MV cable lines began. 110kV cable …
Continue reading “2021 March”
Still severe weather conditions but 20 foundations concreted, halfway point in a while. MV cable laying completed. 110kV cable 50% …
Continue reading “2021 Febuary”
Despite bad weather conditions, implementation of temporary road paving has begun, 12 foundations concreted. MV cable laying at completion – …
Continue reading “2021 January”
The main road works have been completed, 7 foundations are concreted, Work on MV and HV lines is underway. Construction …
Continue reading “2020 December”