At the end of September, production was 265 GWh, which translates into no CO2 emissions into the atmosphere of more than 185,000 tons.
Work is underway on the construction of a village day care center in Biala, and we are waiting for a construction permit for the expansion of the day care center in Biskupice, both of which are being carried out by BBFW under an Agreement with the Municipality. Work on the reconstruction of the district road 1272Z implementation change on the Biskupice-Biala Bor relationship with a length of 3.6 km has been completed. The road has been widened from 3.5m to the targeted 5.5m, with 0.75m wide shoulders on both sides and exits to properties. The road is scheduled to be officially opened in November, even though it is already in use 😊. Both Compensatory Investments and the reconstruction of the district road are BBFW’s contribution to improving the quality of life of residents of the municipality of Biały Bór.