The next stage is behind us On 23 May, BBFW obtained the concession for the production of electricity issued by the President of the Energy Regulatory Authority, from which date the Farm became a full participant in the energy market. At the end of June, production was 216 GWh, which translates into no CO2 emissions into the atmosphere of over 173,000 tonnes.
June saw the start of work on the construction of the village day care centre in the village of Biala, carried out as part of the Compensation Investments that BBFW is carrying out under the Agreement with the Municipality. Work is underway on the reconstruction of the district road 1272Z realising Biskupice-Biala Bór with a length of 3.6 km. The road has already been widened from 3.5m to the target length of 5.5m. What remains to be done is to lay the final layer of the surface, the so-called wearing course, make shoulders and exits to properties. Both the Compensatory Investment and the reconstruction of the district road are BBFW’s contribution to improving the quality of life for the residents of the municipality of Biały Bór.