On September 1, PSE energized the high-voltage cable line connecting the 400/220/110kV Żydowo-Kierzkowo SE ZDK substation with the Bialy Bor GPO BBFW wind farm substation. On the same day, the general contractor ONDE/ERBUD energized the entire substation energizing the power transformer fields, HV reactor, medium voltage switchgear and own needs, Emil thank you 😊. Applying voltage to the GPO is the next step after obtaining the EON permit to allow the farm to work with the power grid. The next step will be to obtain approval for temporary cooperation with the ION grid. By the end of the month, voltage had been given to 10 turbines, which are only waiting for ION permission to start generating. The farm has already installed 23 turbines, more than half of them. The installation is currently being carried out using 3 independently operating crawler cranes with a lifting capacity of 600t each. Biały Bór Sp. z o.o. is also consistently implementing the Compensatory Investment program in accordance with the agreement with the Municipality of Biały Bór. The installation of recreational facilities in the form of playgrounds, outdoor gyms, barbecue shelters is underway, and the replacement of windows in residential facilities included in the window replacement program has begun.