Pre-installation, i.e. the installation of the first two tower segments on all sites, has been completed. Preinstallation was carried out using a 500t wheeled crane. At 12 locations the turbines are assembled in their entirety . Installation took place using 2 independently operating 600t crawler cranes. On 25 August, a transmission agreement was signed between the company Biały Bór Farma Wiatrowa and Polskie Sieci Elektroenergetyczne PSE, and today Biały Bór Farma Wiatrowa was granted permission to supply EON voltage for the D-type generation module. This means that the facility can be supplied with voltage from the PSE-owned substation 400/220/110kV Żydowo-Kierzkowo SE ZDK to the 110kV cable connecting SE ZDK to GPO BBFW. BBFW is the first facility in the country to be connected in full compliance with the new grid code and one of the three largest (in terms of connection capacity) wind farms in the Polish power system. At this point we would like to thank our contract engineer WSP Polska Sp. z o.o., the general contractor consortium of ONDE S.A./ERBUD S.A. and ENERGOPOMIAR-ELEKTRYKA Sp. z o.o. for their involvement in the preparation of the EON application and other documents necessary to reach this stage, special thanks to Ania and Emil for their help and involvement in this matter.