Despite bad weather conditions, implementation of temporary road paving has begun, 12 foundations concreted. MV cable laying at completion – 90% completed. Also, the route of the HV cable is almost 90% ready. The pulling of the 110kV cable into the prepared pipeline has also begun. The construction of the walls of the GPO building has been completed and a large part of the prefabricated foundations of the 110kV apparatus has been installed.